Project Schedule

Fall 2011

  • Christening of the hall
  • Opening of the concert hall featuring the OSM to officially launch its 2011-2012 season

August 2011

  • Provisional delivery of the concert hall (final delivery in August 2012)
  • Beginning of the lapping of the hall

Under Way

  • Mechanical engineering and electricity construction
  • Interior and exterior architecture

Spring 2010

  • Erection of the structure
  • Parking Lot

Fall 2009

Beginning of the construction of the new concert hall

Summer 2009

Construction of the new parking lot and the Grand Foyer culturel of Place des Arts

May 2009

Launching of construction work and demolition of the old parking lot

April 2009

A 29-year partnership agreement is signed with Groupe immobilier Ovation for the design, construction, funding, operation and maintenance of the new concert hall.

February 2009

Submission of funding proposals

Fall 2008

Submission of technical proposals

December 2007

Call for proposals (PDF, 5.0 Mo, 341 p.) to select the partner who will be in charge of the design, construction, funding, operation and maintenance of the new concert hall.

December 2006

Request for qualification (PDF, 5.29 Mo, 86 p.) to select potential partners from the private sector for the design, construction, funding, operation and maintenance of the new concert hall.

June 2006

The Prime Minister of Québec Jean Charest and the Minister of Culture and Communications and Minister responsible for the region of Montréal Line Beauchamp announce the construction of a new concert hall.

2005

The Government of Québec hired experts from the ARTEC firm as acoustics specialists to develop the project.