Progress Report

- The concert hall perches atop the building’s structure like a jewel atop a ring, isolating it from all exterior noise and vibrations.
June 2011
To date, the work has progressed very well, making it possible to hold the first OSM concert on September 7, 2011.
The building envelope will be completed by late July 2011.
The Auditorium work will be completed with the commissioning tests in mid-August so that the orchestra can begin to rehearse on August 26, 2011.
The concert hall foyers will also be completed in mid-August 2011.
The backstage areas and the overall work will be completed in late fall 2011.